Civil Engineering; GRS; Persimmon Homes; Blackburn
10th November 2026
GRS sets the kerb line at Jack Walker Way in Blackburn

GRS Contractors is kerbing the next stretch of estate road at Jack Walker Way in Blackburn, the Persimmon Homes development where it has been on site for a number of months.

The kerbs decide where the road runs and how high it sits. The stone and the tarmac that follow are laid to them. It's simple and easy work for our team but it's important we get it right - many companies don't.
The gang is working to a string line, with our Hitachi Zaxis 135US excavator placing semi-dry concrete along each edge of the road, with our lads levelling it by shovel. The precast kerbs are set on top and backed with more concrete to hold them.
One side of the road is kerbed - we did that last week. The concrete bed is down on the other. The drainage went into the ground first.
It follows the surface water outfall on Hays Lane, which GRS finished in early October after a month-long road closure.
Paul Smalley, Contracts Manager at GRS, said: “Look back at the work we have done here and we’ve made a big difference. This road will look great once the black is down. For now, we crack on. We're proud of what has been achieved on site here in Blackburn. It's not been a straight forward job but we've delivered when it mattered, overcome challenges and our client is happy."
From the top of the road, the view runs straight down over Blackburn.
GRS has more work to do at Jack Walker Way over the next few months. It will then move its gangs on as more sites get going.
Project details
Client: Persimmon Homes
Location: Jack Walker Way, Blackburn
Works: roads and drainage, including the Hays Lane surface water outfall
Kit: Hitachi Zaxis 135US excavator
GRS Contractors delivers roads, sewers, deep drainage and groundworks for housebuilders across the North West and North Wales, and has done for more than 60 years.
To talk to GRS about a scheme, call 01744 410600 or email enquiries@grscontractors.com