4th November 2026
GRS starts S278 highway works for Rowland Homes in Euxton

GRS Contractors has started section 278 highway works on Pear Tree Lane in Euxton, near Chorley, for a new Rowland Homes scheme.

Section 278 works are changes to the public road that let a new development connect to it, built under an agreement with the highway authority. When Rowland Homes kicked off the scheme, they wanted GRS's name on them.
Three weeks in, new kerb lines are in along Pear Tree Lane and the sub-base is down, so the new road is starting to take shape. Ducting is on site and ready to go in next.
It is a smaller job than the big housing schemes GRS is known for, and it is carried out in the public highway rather than inside a site boundary.
Paul Smalley, Contracts Manager at GRS, said: “We are only three weeks in and we are making very good progress.
“We don’t just pick the jobs we do. We help our clients out. It’s not all big housing schemes and developments. It’s jobs like this, sometimes ugly, that we’ll make great for a valued client, and Rowland Homes is one of them.”
Euxton is the latest Rowland Homes scheme for GRS, which is also working for the housebuilder at Royal Gardens in Bispham, Chadderton and Ash Tree Fold in Haydock.
Project details
Client: Rowland Homes
Location: Pear Tree Lane, Euxton, Chorley, Lancashire
Scope: section 278 highway works, including kerbs, sub-base and ducting
Programme: works started in October 2026; three weeks in at the start of November